01
Location Screen
An assessment of 3–5 sites you’re weighing, against one brief. Available capacity, connection window, refusal density, a ranking, questions for the operator. 10 working days, fixed price.
This is the first step.
Pre-launch. ftCEE is just getting started — the site and publications are being built, and the first analyses are coming soon. You’re welcome to get in touch now.Pre-launch — site in progress, first analyses coming soon.
FirmMW is a research programme inside ftCEE. It answers a question Poland has no reliable source for today: where power is actually available, when it can be connected, and what a firm megawatt really costs at a specific location.
This is not an energy-price service, and it is not consulting. It is a maintained body of evidence about the Polish grid — available connection capacity substation by substation, realised connection timelines, refusal density, operators’ development plans — from which we assemble an assessment of a single site.
The name comes from the question the programme solves: what it costs, and how to secure, a firm MW — a megawatt that is there when you need it, in the place you want to build.
Anyone planning a large load — a data centre, a plant electrification, a battery — has to answer three questions before choosing a site. Today each is settled separately, on data that doesn’t fit it.
No one in Poland answers these three together. FirmMW is built to do exactly that.
An energy futures contract or a PPA is a financial instrument on price. It does one thing very well: it locks the cost of a megawatt-hour years ahead and takes price risk off the budget. If your problem is wholesale price volatility, that is the right tool — and FirmMW does not replace it.
But when you’re building a large load, the binding constraint is not price. It’s the queue. You can hedge the price to the cent and still spend two years waiting to connect — because a futures contract does not get you a physical grid connection. Nor does it tell you whether this particular substation will accept 20 MW, or when. And the price you locked is the exchange price at a market hub — not the €92 a firm megawatt actually lands at, under your hall.
These are two different instruments for two different questions. A futures contract manages price over time. FirmMW settles availability in place and time, and computes the full delivered cost the exchange price leaves out. One does not replace the other. But get the order wrong — lock the price before you’ve checked where and when you can connect — and you can end up with a perfect hedge on power you have no way to take.
| Futures / price PPA | FirmMW | |
|---|---|---|
| What it answers | What a megawatt-hour will cost | Where, when and at what cost you secure a firm megawatt |
| Nature | Financial — an instrument on price | Physical — an assessment of availability and connection |
| Unit of reference | Market price at a hub | A specific substation and connection node |
| Binding constraint | Price volatility | The connection queue and timing |
| What it puts in your hands | A locked cost | The decision of where to build, and a real connection window |
| What it won’t do | Won’t get you connected or pick your site | Won’t lock your energy price |
| The cost it shows | The exchange price of energy | The full cost of firm power: shape, firming, balancing, guarantees of origin, network charges |
FirmMW rests on four datasets. Three can be reconstructed from public sources — useful, but not an advantage. The fourth is the advantage, because it compounds by calendar time and exists nowhere else.
Operators publish available capacity every quarter — and each publication overwrites the last. No one archives these files. We archive them from day one, dated and checksummed. After a year we hold a time series of connection-capacity availability in Poland that cannot be bought or reconstructed backwards. Anyone who starts collecting a year after us is a year behind, permanently.
The value of FirmMW comes down to one thing: the difference in quality of a siting decision worth hundreds of millions. Below is the “before” and the “after”.
| Before | After |
|---|---|
| A shortlist from land, incentives and a hunch about the grid | A shortlist ranked by real capacity availability and a credible connection date |
| Energy price in the model = the contract headline | Firm power cost split into seven components, each with a grade of evidence |
| “The operator says it should work” | The distribution of realised connection times for that operator and that class of substation |
| Grid risk as a paragraph in the memo | Grid risk as a numeric component with disclosed weights |
Example: a substation with 118 MW available, hit by two applications of 24 and 30 MW, suddenly has 64 — 118 − 24 − 30. If you need 20 MW, your headroom over the queue dropped from five-fold to three-fold in one quarter — and no energy price contract will ever tell you that.
ftCEE is just getting started, and we don’t pretend to a track record we don’t have. What FirmMW’s credibility rests on from day one is method, not a client count. We publish what can be observed, compute what can be computed, and label the rest with one of five grades of evidence — and never mix a fact with an estimate in the same sentence.
We do not broker electricity, sell projects or earn transaction commissions. Our only product is the assessment. It is the only position from which you can state a number someone will underwrite for ten years.
FirmMW can be bought at three levels. Each makes sense only after the one before — we don’t sell monitoring to someone who hasn’t yet seen how our data moves.
01
An assessment of 3–5 sites you’re weighing, against one brief. Available capacity, connection window, refusal density, a ranking, questions for the operator. 10 working days, fixed price.
This is the first step.
02
A full assessment of one chosen site, with the firm power cost model and scenarios. A section ready for the investment memo.
03
Continuous watch on your nodes. A monthly review and an alert when something material changes at the substation you’re building on.
Send a short brief — capacity, earliest energisation date and the sites you’re considering. We’ll reply within two working days with a first read on what we already know about them. If you’d rather read how we compute things first — start with our analyses.
Two to four substantive emails a month on power availability, grid connections and costs in Poland. Not a company newsletter.